EPC Costing Department Scorecard

Tracking Cost Performance Metrics - EOS Traction Framework

Reporting Period
Q3 2023
Estimate Accuracy
94.2%
Target: 95% +1.2%
Cost Variance
2.8%
Target: ≤3% -0.5%
Change Orders
12
Target: ≤10 +2
Cost Savings
$1.2M
Target: $1M +$0.2M
Cost Metric Target Current Previous Trend Owner Status
Estimate Accuracy
% variance between estimated and actual costs
≥ 95% 94.2% 93.0%
+1.2%
Sarah Chen
Slightly Below
Cost Variance
Deviation from budgeted costs
≤ 3% 2.8% 3.3%
-0.5%
Raj Patel
On Target
Change Order Processing
Avg. days to process change orders
≤ 5 days 6.2 days 7.5 days
-1.3 days
Mike Johnson
Improving
Value Engineering Savings
Savings identified through value engineering
$1M/quarter $1.2M $0.9M
+$0.3M
Elena Rodriguez
Exceeding
Cost Reporting Timeliness
% reports delivered on schedule
100% 98.7% 97.2%
+1.5%
David Kim
On Track
Risk Contingency Utilization
% of contingency budget used
≤ 70% 82.5% 75.3%
+7.2%
Amanda Smith
Attention Needed

Performance Insights

Strong Value Engineering Performance

The Value Engineering team exceeded targets by 20%, identifying $1.2M in savings through material substitutions and process optimizations.

Estimate Accuracy Slightly Below Target

Estimate accuracy is at 94.2% (target 95%). Recent commodity price fluctuations have increased variance in material cost estimates.

Contingency Utilization Exceeding Limits

Risk contingency utilization at 82.5% exceeds the 70% target. Unforeseen site conditions on Project Orion have consumed additional funds.

Critical Action Items

Review Project Orion Contingency

Conduct detailed analysis of contingency usage and develop recovery plan

High Priority Amanda Smith Due: Oct 15

Improve Estimation Process

Implement real-time commodity price tracking for more accurate material cost estimates

Medium Priority Sarah Chen Due: Nov 1

Share Value Engineering Best Practices

Document and share successful cost-saving strategies across all projects

Standard Priority Elena Rodriguez Due: Oct 30

Automate Change Order Processing

Implement new software to reduce processing time to target 5 days

High Priority Mike Johnson Due: Dec 1

Costing Department Performance Summary

Overall department performance remains strong with 4 out of 6 KPIs meeting or exceeding targets. Focus areas include improving estimate accuracy and managing contingency utilization.

83%
Target Achievement
Positive Trends
4 Metrics
Needs Attention
2 Metrics
On Track
4 Metrics