Integrated Project Lifecycle Scorecard

1. Phase Completion Status

Engineering

95%

Procurement

88%

Construction

65%

Commissioning

15%

2. Engineering Deliverables

Document Status Revision Approval Due RFIs
P&ID Drawings Approved Rev 3 2023-11-15 2 Open

3. Procurement Status

POs Issued

145

Vendor OTIF

92%

Material Receipt

78%

4. Production Tracking

Component Type Qty Completed QC Pass % Delivery Status
Pressure Vessel Subcontracted 8/10 100% In Transit

5. Construction Progress

Workfront Completion

65%

Safety Incidents

3

Rework %

4.2%

6. Commissioning Tracker

System FAT SAT Punch Items Handover Status
Utility Systems Passed Pending 12 Delayed

7. O&M Readiness

Training Completed

85%

Spares Inventory

92%

Warranty Coverage

78%

8. Project Risk & Actions

Critical Risks

  • Construction delay impacting commissioning (15 days)
  • Pending vendor drawings for electrical systems

Recovery Plans

  • Implement 24/7 construction shifts
  • Expedite material delivery through air freight

* Integrated with Primavera & SAP | Next project review: 2023-11-15 09:00