Sales Order |
Project Item |
Department |
Predecessor |
Successor |
Planned Start |
Actual Start |
Planned End |
Actual End |
Duration |
Deadlock |
#ORD-2425-8765 |
ENG-001 |
Engineering |
- |
PROC-001 |
2024-06-01 |
2024-06-01 |
2024-06-15 |
2024-06-18 |
15 days |
⚠️ 3 days |
PROC-001 |
Procurement |
ENG-001 |
MFG-001 |
2024-06-16 |
2024-06-19 |
2024-06-30 |
2024-07-05 |
15 days |
⚠️ 5 days |
MFG-001 |
Manufacturing |
PROC-001 |
CON-001 |
2024-07-01 |
2024-07-06 |
2024-07-20 |
- |
20 days |
⚠️ Waiting |
CON-001 |
Construction |
MFG-001 |
SW-001 |
2024-07-21 |
- |
2024-08-10 |
- |
21 days |
- |
SW-001 |
Software |
CON-001 |
- |
2024-08-11 |
- |
2024-08-25 |
- |
15 days |
- |
📌 Key Metrics
- On-Time Delivery: 60%
- Average Delay: 4.2 days
- Active Deadlocks: 3
- Critical Path Duration: 86 days
Legend:
On Track |
Delayed |
Upcoming
⚠️ Deadlock Indicators: Material Delay (Red), Resource Conflict (Orange), Approval Pending (Yellow)